CONDITIONS OF A SINGLE INTAKE DESCENDING OF INTERMEDIATE CASING STRINGS OF AN EXCESSIVE WEIGHT COMPARED TO A DERRICK LOAD CAPACITY
DOI:
https://doi.org/10.26906/znp.2018.50.1078Keywords:
drill string, borehole, drilling fluid centralizerAbstract
The way of the intermediate casing string descending is considered. It allows overcoming the limits of derrick load capacity through the weight transferring descending intermediate casing string on the cemented string that is based on the foundation. In particular, technology is developed where the weight of each additional string, as it builds-up, is equivalent to additional friction forces which arise in the enlarged area. Such a descent technology does not depend on the load capacity of the derrick load capacity, does not create loads on the basis of derricks as well as additional tensile loads in the string with an increase in its length. It is proved that if such a condition is met, all known restrictions for the descent of intermediate columns of any length in a single intake are removed. Authors determined descending casing string weight that is distributed over the previously installed and cemented string. It is suggested to distribute casing string weight on existing and cemented string.
References
Рекордний спуск 14" обсадної колони // Oil and Gas. − 1973. – № 206. – Р. 54.
Досвід проектування, випробування і планування рекордного спуску обсадної колони діаметром 508 мм // SPE, Drill, End. – 1988. – № 2. – Р. 187 – 194.
Мильштейн В. М. Цементирование буровых скважин / В. М. Мильштейн. − Краснодар : НПО «Бурение», 2003. − 286 с.
Мильштейн В. М. Трехсекционная универсальная цементировочная головка с приставным коллектором ЗУЦГК-168-40 / В. М. Мильштейн, В. Б. Лазарев // Строительство нефтяных скважин на суше и на море. − 2005. − № 5. − С. 26 − 27.
Патент 439112 США МКИ Е21 В 33/16. Устройство для спуска обсадной колонны в скважину; опубл. 31.12.1968. Бюл. № 2.
Світалка П. І. Опис до деклараційного патенту України на винахід 48623 Е21В17/10 Центратор розвантажувальний для колони труб у свердловині / Світалка П. І., Рибчич І. Й., Нєвєжин В. В., Соловйов В. В.; опубл. 18.08.2002. Бюл. № 8.
Smith R. С. Checklist aids successful primary cementing / R. С. Smith // Oil and Gaz Journal. – Tulsa, Amoco Production Co., 2008. – № 1. Vol. 80. – P. 30 – 33.
ISSN 0030-1388
Alimzhanov M. T. Methods of continuum nonlinear mechanics in problems of rock pressure control at drilling deep Holes / M. T. Alimzhanov // Advances in Mechanics: Int. Jour. – Warsaw, 1992. − Vol. 15., № 3-4. − P. 41 − 69.
Tester J. Oil and gas well drilling [web resource]/ J. Tester, G. Stutz, Ch. Augustine, etc // Shale gas module – Spring 2011. – Massachusetts, 2011. – 51 p.
Kennedy R. Shale gas challenges. Technologies over the asset life cycle [web resource] / R. Kennedy // U.S.-China Oil and Gas Industry Forum. – 2010. – P. 36. https://www.usea.org/articles